Document colectat · PNRR România, plan și decizii
Commission Staff Working Document: Analysis of the recovery and resilience plan of Romania amending the approval of the assessment of the recovery and resilience plan of 29 October 2021
- Instituția sau publicația sursă
- PNRR România, plan și decizii
- Data preluării
- 26.09.2026 17:53
- Dimensiunea materialului
- 643,8 KB
Conținutul disponibil în colecție
Textul documentului
riterion 2.8 of Annex V to the RRF Regulation.
3.9. Costing
Romania has provided individual estimated costs for all the measures in the REPowerEU chapter.
Apart from the measures in the REPowerEU chapter, there are no new measures. Romania has
also provided individual justifications for all the measures whose modifications entailed a change
in the cost estimates or related milestones and targets, including on the proportionality of the
relevant amendments.
The cost information provided by Romania is mostly sufficiently detailed and substantiated.
Romania provided estimates and assumptions on costs using the standard template table, which
was intended to summarise the key information and evidence on costing. Descriptions of the
methodology underlying the cost calculations are found in a document which Romania submitted
separately.
Romania also submitted additional documents and materials intended to clarify costing
discrepancies and provide costing data and benchmarks on comparable investments done in the
past or in other countries. These documents also include descriptions and explanations of the main
drivers and changes in the costs of the amended measures and their proportionality.
Reasonable costs
Overall, assumptions used by Romania to estimate the costs of the measures in the REPowerEU
chapter provide a reasonable explanation of their primary cost drivers. The provided materials
generally allow to identify the methodology used in costing calculations, even if for a small number
of measures this information is missing or not as clear. Nevertheless, there is no concrete evidence
that would put into question the costing estimates provided.
23
Measures in the REPowerEU chapter, comply with the eligibility criteria set out in the RRF
Regulation. All costs are incurred into after February 2022. Value-added tax (VAT) is not included
in any of the cost estimates. The reasonability of the costs of the modified measures has not
changed from the initial assessment of these measures. Changes in the cost estimates for all of
them are duly justified and proportional. In the case of measures whose costs are being amended
under Article 21(1) of the RRF Regulation, sufficient information has been provided to justify the
objective circumstances and the proportionality of the changes in the cost estimates or related
milestones and targets. In this context, the reasonability of the cost estimates, taking into account
the new measures in the REPowerEU chapter and the amended measures, has been established to
a medium extent.
Plausible costs
The amount of the estimated costs in the REPowerEU chapter, is in line with the nature and type
of the envisaged reforms and investments. Romania provided supporting documents and evidence
to substantiate the cost estimates for most of the new measures in the REPowerEU chapter.
However, additional information on the plausibility of cost estimates was necessary in instances
where the given explanations were not detailed or substantiated enough for plausibility to be
established.
The plausibility of the costs of the modified measures has not changed from the initial assessment
of these measures, as the changes in the cost estimates for all of them are duly justified and
proportional. Sufficient information has been provided to justify the objective circumstances and
the proportionality of the changes in the cost estimates or related targets. Considering the
limitations of an ex-ante assessment of cost estimates, the financing amounts were deemed
appropriate.
No double Union financing
Romania has indicated that the costs for the new measures in the REPowerEU chapter will not be
funded at the same time by other Union funding sources. The commitment to put in place
safeguards which are meant to prevent double funding remain and has not been altered by the
plan’s modification.
Commensurate and cost-efficient costs
The total cost of the modified Romanian RRP is commensurate to the expected social and
economic impact of the envisaged measures. The plan is expected to effectively address a
significant subset of challenges identified in the CSRs. The main objectives of the plan are to foster
the twin transition, address bottlenecks to a lasting and sustainable growth, job creation and
economic, social and institutional resilience, thereby reducing vulnerability to shocks. The plan
contributes to strengthening social cohesion and social protection and to the implementation of the
European Pillar of Social Rights. The plan enhances the economic, social and territorial cohesion
and convergence within the Union. The economic and social impact of the plan in combination
with the positive cost assessment, indicates that its cost is in line with the principle of cost-
efficiency.
24
***
The justification provided by Romania on the amount of the estimated total costs of the modified
recovery and resilience plan is to a medium extent reasonable, plausible, in line with the principle
of cost-efficiency and is commensurate to the expected national economic and social impact.
Romania provided sufficient information and evidence that the amount of the estimated cost of the
reforms and investments of the modified recovery and resilience plan to be financed under the
Facility is not covered by existing or planned Union financing. This would warrant a rating of B
under criterion 2.9 of Annex V to the RRF Regulation.
3.10. Controls and audit
The original assessment on the robustness and adequacy of the control system and other
arrangements included in the Romanian RRP had concluded that these arrangements were
adequate subject to the timely fulfilment of two milestones pertaining to the setting up of a
repository system for the collection of data in line with art 22(2)(d) of the RRF Regulation and
entry into force of the mandate of the main institutions implementing and controlling the Romania
RRP. This warranted a rating of A under assessment criterion 2.10 of Annex V to the RRF
Regulation.
The Romanian authorities have confirmed that the internal control system, as well as the
arrangements for the prevention, detection and correction of fraud, corruption, conflict of interest
and double funding as previously assessed remain in place. In addition, as provided by the first
relevant milestone included in the Annex to the original Council Implementing Decision, a
Government Ordinance provided the Ministry of Investments and European Projects with the legal
mandate to act as coordinating body and laid down the roles of the Ministry of Finance and the
Audit Authority. In compliance with the second milestone, a repository system for monitoring the
implementation of the RRP has been set up, including for the collection and storage of data
required by Article 22(2)(d), points (i) to (iii). The adequacy of these measures has been assessed
positively by the Commission in the context of the first payment request, including through
commitments fulfilled by the second payment request.
The modifications to the original plan and the introduction of the REPowerEU chapter as such do
not affect the original assessment. However, in the context of the modifications to the Romanian
RRP, its audit and control system needs to be reassessed. Since the original assessment, the
Commission has had access to information on its actual implementation. This includes the
preliminary findings of the audit on the protection of the financial interests of the Union performed
by the Commission in Romania.
In light of this information, the Commission considers that the internal control system of
Romania’s RRP is overall adequate.
Robustness of internal control system and distribution of roles and responsibilities
The previously assessed arrangements as regards the roles and responsibilities of the actors for
control and audit, the segregation of functions and independence of actors performing audits
25
remain adequate and were further enhanced through the entry into force of the Government
Ordinance enacting the legal mandate of the Ministry of Investments and European Projects as
coordinating body, and of the Ministry of Finance and the Audit Authority.
Adequacy of control systems and other relevant arrangements
The control system and other arrangements to prevent, detect and correct fraud, corruption and
conflicts of interest when using funds provided by the Recovery and Resilience Facility continue
to appear overall adequate. The implementation of an IT system for the monitoring and control of
the measures, as well as for the collection of data in line with the requirements set out in Article
22(2)(d), points (i) to (iii) of the RRF Regulation is confirmed.
Adequacy of arrangements to avoid double EU funding
The previously assessed arrangements as regards the prevention, detection and correction of
double funding remain in place as initially assessed by the Commission.
Legal empowerment and administrative capacity of control function
The legal mandates of all the institutions involved in implementation, control and audit have been
approved by means of a Government Emergency Ordinance3. In line with this Ordinance, the
Ministry of Investments and European Projects, as coordinating body, exercises all the tasks
related to the monitoring, verification, control and recovery, and to the drawing up and signing of
payment requests and management declarations. The implementation of the RRP is ensured by
line ministries and their subordinated structures, through financing agreements with the Ministry
of Investments and European Projects. Audits are entrusted to the audit authority within the Court
of Accounts. This body is the same audit authority as the one used for the European Structural and
Investment (ESI) funds. Its independence from the coordinating body and the institutions
responsible for the implementation of the reforms and investments is confirmed.
***
The nature and extent of the proposed modifications to Romania’s recovery and resilience plan do
not have a material impact on the previous assessment (rating of A) of the adequacy of the control
and audit arrangements proposed by Romania, as reflected in the previous SWD(2021)276 final.
3.11. Coherence
The modifications to Romania’s RRP, in particular those related to green transition and the newly
added REPowerEU chapter do not affect the overall coherence of the plan.
3
Emergency Ordinance No 124 of 13 December 2021 on the financial stability of financial institutions
and institutions for the management of European funds allocated to Romania under the recovery and
conversion mechanism and amending Government Emergency Order No 155/2020 as regards the
development of the Recovery and Recovery, Recovery and Reduction Plan required by Romania for
access to the foreign and reimbursable business space and to the budget of the Land of the Recovery and
Recovery and Recovery Mechanism
26
For all key areas included in the Romanian RRP – green economy, education, business
environment, health, social inclusion, public administration, and digitalisation – an explicit and
coherent explanation of their respective contribution to the six pillars in Article 3 of the RRF
Regulation is provided. The main focus of the Romanian RRP is unchanged, as green transition
and digital transformation remain at its core, where the green reforms and investments included in
the original RRP components are boosted by the new REPowerEU measures. Digital reforms and
investments remain focused on supporting areas with the largest investment gaps such as
digitalisation of public services and schools.
The REPowerEU measures are coherent with Romania’s policy framework aimed at reducing
greenhouse gas emissions and increasing the share of renewable energy sources. They also
reinforce the measures included in the original RRP on energy efficiency and strengthening the
electricity network by increasing the share of renewable energy and decreasing energy demand.
The modifications to the RRP display coherence within the components, maintained throughout
the overall structure and objectives of the plan.
***
Taking into consideration the qualitative assessment of all components of Romania’s modified
recovery and resilience plan, their individual weight (importance, relevance, financial allocation)
and their interactions, the plan contains measures for the implementation of reforms and public
investments which, to a high extent, represent coherent actions. This would warrant a rating of A
under the assessment criterion 2.11 of Annex V of the RRF Regulation
3.12. REPowerEU
Romania’s REPowerEU chapter is expected to have a lasting impact on reducing fossil fuel
consumption and greenhouse gas emissions and increasing the uptake of renewable energy. The
chapter includes an important reform aiming at facilitating the identification of acceleration areas,
for a swifter deployment of new renewable energy plants. This reform is complemented by two
investments aimed at deploying renewable energy. The plan also includes setting up one-stop-
shops dedicated to providing information and assistance to individuals for the installation of
renewable energy equipment and for energy efficiency renovations. This reform is complemented
by an investment aimed at deploying solar energy on single-family residential buildings, and two
investments to improve energy efficiency in the country by renovating public and private buildings
respectively.
By financing an investment aiming at improving the electricity network, the REPowerEU chapter
submitted by Romania aims to improve the maintenance and efficacy of the transmission network,
facilitating the connection of new renewable energy plants and ensuring better security and
reliability of the infrastructure.
Energy poverty is addressed by the introduction of an investment setting up a grant voucher
scheme to make energy efficiency improvements to households, with a focus on vulnerable energy
consumers and households affected by energy-poverty.
27
The plan is also expected to contribute to an accelerated requalification of the workforce towards
green skills with a focus on developing skills in clean technologies needed for the deployment and
use of renewable energy sources.
The REPowerEU chapter is coherent with Romania’s original RRP and extends its ambition in
terms of green transition. The chapter further increases the ambition of component 5 (Renovation
wave) of the original plan with a focus on energy efficiency renovation of public buildings. The
chapter continues to support Romania’s effort to greening its energy mix with two reforms to
simplify the procedures necessary for renewable energy deployment.
Finally, consultations were held with relevant stakeholders in the preparation of the REPowerEU
chapter. An inter-ministerial working group was set-up to prepare the plan. The draft was presented
to the RRP monitoring committee composed of representatives of non-governmental organisations
and representative trade unions and employers’ associations, representatives of associations of
local public administration (National Union of County Councils of Romania, Association of
Romanian Municipalities, Association of Romanian Towns/Small Urban Municipalities and
Association of Rural Municipalities of Romania), as well as representatives of the Economic and
Social Council. They had the opportunity to make suggestions. In March, a public consultation
was organised, as well as a public event with the participation of business representatives, civil
society and stakeholders. Comments and proposals were sent by stakeholders to the Ministry of
Investments and European Projects. Following these consultations, a new draft of the chapter was
prepared.
***
Taking into consideration the assessment of all the measures envisaged in the REPowerEU
chapter, the chapter is expected, to a large extent, to contribute effectively to energy security, the
diversification of the Union’s energy supply, an increase in the uptake of renewables and in energy
efficiency, an increase of energy storage capacities or the necessary reduction of dependence on
fossil fuels before 2030. This would warrant a rating of A under criterion 2.12 of Annex V to the
RRF Regulation.
3.13. Cross-border or multi-country dimension or effect
Most measures included in Romania’s REPowerEU chapter have a multi-country or cross-border
dimension. The REPowerEU chapter is expected to contribute to reducing dependency on fossil
fuels and to reducing energy demand. In particular, a majority of the measures in the REPowerEU
chapter support the deployment of renewable energy sources and reduction of energy demand in
buildings.
The estimated costs of the measures with a multi-country dimension or effect included in the
REPowerEU chapter represent 96.5% of the total estimated cost of the chapter, which is
significantly above the 30% indicative target.
28
Table 3 – Cross-border or multi-country dimension of REPowerEU measures
REPowerEU measure Costs (EUR Contribution to the
million) target in %
Creating a legal framework for the use of state land 3.01 0%
as acceleration areas for RES investments
Setting up one-stop-shops (OSS) to provide energy 0%
advisory services for energy ef
← Înapoi la începutul extrasului
Extrasul poate avea altă structură decât documentul original. Data preluării nu reprezintă perioada statistică sau data publicării de către instituție.
Identificarea exactă a documentului colectat
Amprenta SHA-256 permite identificarea versiunii preluate.
9c9d979fe9e2d01f6ddc8a83e0984ff9c88984a9b50c39b11bd53f73a86c3d3e