Service infrastructures of other operators

Instituția sau publicația sursă
Documentul de referință al rețelei feroviare 2026
Data preluării
26.09.2026 17:56
Dimensiunea materialului
3.245,5 KB

Conținutul documentului colectat

Secțiuni și tabele

                                        Compania Naţională de Căi Ferate “CFR” S.A.                                                           România
                                       Name                         Lines 1, 2, 3, 4, 5, 6, 7
                                       Location                 Railport Arad
                                       Operating program (time) 2009-present
3.2   Railway Infrastructure                                       Line1: usable length 650m; Line2: usable length 630m; Line3: usable length 620m; Line4: usable length 600m;
                                       Technical specification   line5: usable length 570m; line6: usable length 600m; line7: usable length 560m.
                                       Planned changes in the
                                       near future                  extension of railway lines.

4. Tariffs 4.1.1 Handling fee: 4.1.1.a Container handling/32€; 4.1.1.b Semi-trailer handling/37€;

4.1   Tariffs information              4.1.2 Storage rate: 4.1.2.a Container storage 5€/day (day of arrival + 2 days free of charge);
                                       4.1.3 Tariff for parking wagons: 4.1.3.a Wagon on 4 axles: 5€/day (free arrival day); 4.1.3.b.Wagon on 6 axles: 10 €/day.
      The information of the tariff
4.2                                    Not applicable
      discount rates
                                       5. The access conditions
5.1   Legal requests                   On the basis of contracts.
                                       5.2.1 Technical conditions for railway access: a. Maximum permissible gasket length 740m; b. Permissible load/axle 22,5t; c. Minimum
                                      radius of registration in curve 190m.
5.2   Technical conditions
                                       5.2.2 Technical conditions for road access: a. the limit of the length of the 45ft container; weight limit 45t; b. Swap bodies: length limit
                                      13,6m; weight limit 45t; c. Semi-trailer: length limit 13,6m; weight limit 45t.
5.3   Authorization of the services    This is not the case.
5.4   IT Systems                       Railport uses its own program/software, both for monitoring rail traffic and road traffic, called Railcont.
                                       6. The allocation of the service capacities
6.1   Requesting Access                By request for offer and signing the contract.
6.2   The request`s reply              In 5 working days.
                                       Available capacities about 25% free of the existing volume.
6.3

Valorile și formulările aparțin documentului citat. Data preluării nu reprezintă perioada datelor sau data publicării de către instituție.

Identificarea exactă a documentului colectat

Amprenta SHA-256 permite identificarea versiunii preluate.

13291ad19fcb65b555c62feac198b5de58984ed7562c85f86d1be72b44ffd963