Infrastructure section with congested capacity
- Instituția sau publicația sursă
- Documentul de referință al rețelei feroviare 2026
- Data preluării
- 26.09.2026 17:55
- Dimensiunea materialului
- 503,4 KB
Conținutul disponibil în colecție
Textul documentului
frastructure with saturated capacity.
C.2 Description of the sections declared as congested capacity infrastructure by CFR
C.2.1 Tăndărei - Feteşti Section
1 Route name Urziceni – Ţăndărei - Feteşti
2 Route Code 804
3 Origin station of the congested capacity infrastructure Tăndărei
4 Terminus station of the congested capacity Feteşti
infrastructure
5 Date of the declaration as congested capacity July 01, 2023 Order no.
infrastructure and the declaration modality 86/June 23, 2023, of the Director
General of CFR
6 Estimated date for the end of congestion Date of completion of works
CFR Network Statement - 2026 ANNEX 21 Version: 15.1.0 Update: 08.01.2026 Pag: 6 / 15
Compania Naţională de Căi Ferate “CFR” S.A. România
7 Reason for declaring the congested capacity Decrease in circulation capacity from
infrastructure the reason for carrying out the
rehabilitation works
8 Capacity after the declaration as congested capacity Passenger:
infrastructure - season: 6 pairs of trains
- off-season: 3 pairs of trains
Freight: - season: 14 pairs of trains
- off-season: 15 pairs of trains
9 Number of the RUs’ path requests for the congested Passenger:
infrastructure section at the time of declaration - season: 6 pairs of trains
- off-season: 3 pairs of trains
Freight: 74 pairs of trains
10 The priority criteria in allocating the capacities of They are set down by means of the Order
infrastructure during the saturation period of the Minister of Transport and
Infrastructure
11 Infrastructure capacity enhancement plan (Art 51 of the Feteşti station rehabilitation project
Law no. 202/2016)
12 The expected practical capacity after the application of the Passenger: 15 pairs of trains
plan to increase infrastructure capacities and the lifting of Freight: 108 pairs of trains
the saturated infrastructure declaration
C.3 Additional priority criteria for the allocation of infrastructure capacity on the sections
with congested capacity infrastructure
(Art. 47(3) of the Law no. 202/2016)
The priority criteria that apply for the operational distribution of infrastructure capacities during the period of
declaring the Tăndărei - Fetești section as infrastructure with saturated capacity are established by MTI Order
no. 1165/2012 presented in Annex 22 to the Reference Document of the Network.
D. SIMERIA – GLOGOVAT – SECTION
D.1 Declaration of the infrastructure sections with congested capacity
Due to the fact that, after the coordination of the paths (in accordance with art. 46 of the law 202/2016) and
after the consultations with the applicants, it was established that a favourable response to all the requests for
infrastructure capacity for the Simeria - Glogovăţ Section was impossible, in accordance with art. 47 of the law
202/2016, CFR, by Disposition no. 22/2018 of the Director General of CFR, declared Simeria - Glogovăţ
infrastructure section as congested capacity infrastructure.
D.2 Description of the sections declared as congested capacity infrastructure by CFR
D.2.1 Simeria - Glogovat Section
1 Route name Curtici - Coşlariu
2 Route Code 200
CFR Network Statement - 2026 ANNEX 21 Version: 15.1.0 Update: 08.01.2026 Pag: 7 / 15
Compania Naţională de Căi Ferate “CFR” S.A. România
3 Origin station of the congested capacity infrastructure Simeria
4 Terminus station of the congested capacity Glogovăţ
infrastructure
5 Date of the declaration as congested capacity March 01, 2018,
infrastructure and the declaration modality Order no. 22/13.02.2018, of the Director
General of CFR
6 Estimated date for the end of congestion The date of the work completion
7 Reason for declaring the congested capacity The reduction in the traffic capacity due
infrastructure to the rehabilitation works
8 Capacity after the declaration as congested capacity Passenger: 20 pairs of trains
infrastructure Freight: 7 pairs of trains
9 Number of the RUs’ path requests for the congested Passenger: 25 pairs of trains
infrastructure section at the time of declaration Freight: 12 pairs of trains
10 Priority criteria regarding the allocation of infrastructure They are set down by means of the Order
capacity during the congestion period of the Minister of Transport and
Infrastructure
11 Infrastructure capacity enhancement plan (Art 51 of the The rehabilitation project for the
Law no. 202/2016) PanEuropean Corridor IV, the Frontier –
Curtici – Simeria Section, Simeria –
Glogovăţ Route
12 Estimated capacity after the application of the Passenger: 50 pairs of trains
infrastructure capacity enhancement plan and the cease Freight: 100 pairs of trains
of the declaration as congested infrastructure
D.3 Additional priority criteria for the allocation of infrastructure capacity on the sections
with congested capacity infrastructure
(art.47(3) of the 202/2016 Low)
The priority criteria that apply to the operational allocation of infrastructure capacity during the time period of the
declaration of the Simeria-Glogovăţ Section as congested capacity infrastructure are set down in the Order of
the Minister of Transport and Infrastructure no. 1165/2012 presented in Annex 22 to the Network Statement.
CFR Network Statement - 2026 ANNEX 21 Version: 15.1.0 Update: 08.01.2026 Pag: 8 / 15
Compania Naţională de Căi Ferate “CFR” S.A. România
E. BRAȘOV – SIGHIȘOARA – SECTION
E.1 Declaration of the infrastructure sections with congested capacity
Considering the provisions of GD no. 1696/2006 on the approval of the Regulation for the allocation of railway
infrastructure capacities, taking into account the requests of contractors performing rehabilitation works on the
highway CF 300 Brașov - Apața şi Cața - Sighișoara, regarding the closure of a traffic wire, by order of the General
Director no. 94 / 03.07.2020, the infrastructure section Brașov - Sighișoara is declared as infrastructure with
saturated capacity, starting with August 1, 2020.
E.2 Description of the sections declared as congested capacity infrastructure by CFR
E.2.1 Brașov - Sighișoara Section
1 Route name București - Oradea
2 Route Code 300
3 Origin station of the congested capacity infrastructure Brașov
4 Terminus station of the congested capacity Sighișoara
infrastructure
5 Date of the declaration as congested capacity August 01, 2020,
infrastructure and the declaration modality Order no. 94/03.07.2020, of the Director
General of CFR
6 Estimated date for the end of congestion The date of the work completion Trim II
2024
7 Reason for declaring the congested capacity The reduction in the traffic capacity due
infrastructure to the rehabilitation works
8 Capacity after the declaration as congested capacity Passenger: 9 pairs of trains
infrastructure Freight: 9 pairs of trains
9 Number of the RUs’ path requests for the congested Passenger: 12 pairs of trains
infrastructure section at the time of declaration Freight: 14 pairs of trains
10 Priority criteria regarding the allocation of infrastructure They are set down by means of the Order
capacity during the congestion period of the Minister of Transport and
Infrastructure
11 Infrastructure capacity enhancement plan (Art 51 of the Rehabilitation of the Braşov-Simeria
Law no. 202/2016) railway line, component of the Rhine-
Danube Corridor, Braşov-Sighişoara
Section, subsections: 1. Brașov-Apaţa and
3. Caţa-Sighişoara subsections: 1. Braşov-
Apaţa and 3. Caţa-Sighişoara
12 Estimated capacity after the application of the Passenger: 50 pairs of trains
infrastructure capacity enhancement plan and the cease Freight: 100 pairs of trains
of the declaration as congested infrastructure
CFR Network Statement - 2026 ANNEX 21 Version: 15.1.0 Update: 08.01.2026 Pag: 9 / 15
Compania Naţională de Căi Ferate “CFR” S.A. România
E.3 Additional priority criteria for the allocation of infrastructure capacity on the sections
with congested capacity infrastructure
(art.47(3) of the 202/2016 Low)
The priority criteria that are applied for the operative distribution of the infrastructure capacities during the
declaration of the Brașov - Sighișoara section as infrastructure with saturated capacity are established by the
MTI Order no. 1165/2012 presented in Annex 22 to the Network Reference Document.
F. CHIAJNA - VIDELE – SECTION
F.1 Declaration of the infrastructure sections with congested capacity
In the next period, the works to eliminate speed restrictions on the Chiajna - Videle railway section will begin.
Because, during the period of the works, the traffic capacity on this section will be significantly limited, and after
coordinating the routes (cf. art. 46 of Law 202/2016) and after consulting the applicants, it was found that the
favorable satisfaction of all requests for infrastructure capacities for Chiajna – Videle is impossible, in
accordance with the provisions of art. 47 of Law 202/2016, CFR, by Provision no. 93 of 17.07.2023 of the General
Director of the CFR, declared the Chiajna – Videle infrastructure section to be infrastructure with saturated
capacity.
F.2 Description of the sections declared as congested capacity infrastructure by CFR
A.3.1 București Nord – Aeroport H. Coandă T1 Section
1 Route name Bucureşti – Craiova – Timişoara
2 Route Code 100
3 Origin station of the congested capacity infrastructure Chiajna
4 Terminus station of the congested capacity Videle
infrastructure
5 Date of the declaration as congested capacity August 07, 2023
infrastructure and the declaration modality Order no. 93/17.07.2023, of the Director
General of CFR
6 Expected date for end of saturation December 09, 2023
7 Reason for declaring the congested capacity Decrease in circulation capacity due to
infrastructure rehabilitation works
8 Capacity after the declaration as congested capacity Passenger: 29 pairs of trains
infrastructure Freight: 15 pairs of trains
9 Number of the RUs’ path requests for the congested Passenger: 32 pairs of trains
infrastructure section at the time of declaration Freight: 95 pairs of trains
10 Priority criteria regarding the allocation of infrastructure They are established by Order of the
capacity during the congestion period Minister of Transport and Infrastructure
11 Infrastructure capacity enhancement plan (Art 51 of the Speed restriction removal works
Law no. 202/2016)
CFR Network Statement - 2026 ANNEX 21 Version: 15.1.0 Update: 08.01.2026 Pag: 10 / 15
Compania Naţională de Căi Ferate “CFR” S.A. România
12 Estimated capacity after the application of the Passenger: 50 pairs of trains
infrastructure capacity enhancement plan and the cease Freight: 100 pairs of trains
of the declaration as congested infrastructure
F.3 Additional priority criteria for the allocation of infrastructure capacity on the sections with
congested capacity infrastructure
(art.47(3) of the 202/2016 Low)
The priority criteria that applied for the operational allocation of infrastructure capacities during the period of
declaring the Chiajna - Videle section as infrastructure with saturated capacity are established by MTI Order no.
1165/2012 presented in Annex 22 to the of the Network Statement.
G. LUGOJ – TIMISOARA - ARAD – SECTION
G.1 Declaration of the infrastructure sections with congested capacity
In the next period, rehabilitation works will begin on the railway section Lugoj - Timisoara - Arad.
Because, during the works, the traffic capacity on this section will be significantly limited, and after coordinating
the routes (cf. art. 46 of Law 202/2016) and after consulting the applicants, it was found that the favorable
satisfaction of all requests for infrastructure capacities for Lugoj – Timisoara – Arad is impossible, in accordance
with the provisions of art. 47 of Law 202/2016, CFR, by Provision no. 151 of 24.10.2023 of the General Director
of the CFR, declared the infrastructure section Lugoj - Timisoara - Arad as infrastructure with saturated capacity.
G.2 Description of the sections declared as congested capacity infrastructure by CFR
A.3.2 București Nord – Aeroport H. Coandă T1 Section
1 Route name Bucureşti – Craiova – Timişoara – Jimbolia;
Timişoara – Arad
2 Route Code 100; 218
3 Origin station of the congested capacity infrastructure Lugoj
4 Terminus station of the congested capacity Arad
infrastructure
5 Date of the declaration as congested capacity December 10, 2023
infrastructure and the declaration modality Or
← Înapoi la începutul extrasului
Extrasul poate avea altă structură decât documentul original. Data preluării nu reprezintă perioada statistică sau data publicării de către instituție.
Identificarea exactă a documentului colectat
Amprenta SHA-256 permite identificarea versiunii preluate.
8f7ac93a6675bbc0418f68a8b1e1dd3742b4f4e296886a99d044688d6acdc88f