         Compania Nationala de Cai Ferate “CFR” S.A.                                              Romania

7.3.8.6. Capacity Allocation

The priorities regarding the access to the maritime port facilities held by CFR in case of large flows of goods (such as the Constanța Port Railway Complex) are established by the port operators that hold/operate the loading/unloading facilities depending on the availability of storage/operation capacities or the provision of transport ships.

Moreover, the priority of receiving the trains in the stations of the Constanța Port Railway Complex is also established by the port operators depending on the elements shown above, in an IT application developed by SC Informatica Feroviară SA and CFR.

Relief Facilities

CFR supplies the service related to the relief facilities in accordance with Annex II, item 2(h) of Law No. 202/2016.

7.3.9.1. General Information CFR’s relief facilities are placed in the following locations: a) The 20 relief trains equipped with railway cranes are stored in the Bucharest, Craiova, Deva, Cluj, Brașov, Pașcani, Galați and Constanța stations. b) The 8 relief wagons (simple or with hydraulic winches) are stored in the Bucuresti Triaj, Craiova, Cluj and Brașov stations. c) The 33 (simple and hydraulic) snow ploughs are stored in the stations of the Regional Railway Branches 1-8. d) The 129 power cars and relief means and the 75 tower wagons are stored in specialized facilities in the stations of the Regional Railway Branches 1-8.

7.3.9.2. Services The service of supplying relief facilities represents one of the basic services (in accordance with Article 3 of EU Regulation 2107/2177), and involves the quick and efficient intervention with specialized railway means with a view to removing the consequences of the railway accidents, the railway events or of the damage to the elements of the railway infrastructure that may endanger the railway traffic safety. The purpose of the interventions is to restore the traffic safety conditions in the affected areas, and to ensure the continuity of the railway traffic with a view to reducing the disturbances in the traffic of the passenger and freight trains. The servicing of the relief means is provided by the specialized staff of CFR on a permanent basis. In case of the works for removing the consequences of the railway accidents/events, the coordination of the relief trains equipped with railway cranes and the relief wagons is ensured by the General Inspectorate of Railway Traffic Safety of CFR.

7.3.9.3. Service Facility Description CFR holds the following relief facilities: A. trains equipped with railway cranes, with a load between 20 and 250 tons; B. relief wagons equipped with mechanized relief equipment and machinery; C. relief train with wagons with hydraulic winches;

2026 CFR Network Statement           Version: 15.1.6              Section: Service Facilities            A Page
                                     Date:    29.05.2026                                                96 of 98

Valorile și formulările aparțin documentului citat. Data preluării nu reprezintă perioada datelor sau data publicării de către instituție.