74 Water management permit for the sub- Water management permit (aviz de
project “Correction of torrents Valea gospodarire a apelor) for the sub-project,
Lungă”. issued by the Water Basin Administration
(Administrația Bazinală de Apă) Olt and
dated 1 August 2022.
75 Water management permit for the sub- Water management permit (aviz de
project “Correction of torrents Izvorul gospodarire a apelor) for the sub-project,
Govorei”. issued by the Water Basin Administration
(Administrația Bazinală de Apă) and dated
31 January 2020.
76 Water management permit for the sub- Water management permit (aviz de
project “Correction of torrents Bistricioara, gospodarire a apelor) for the sub-project,
stage II”. issued by the Water Basin Administration
(Administrația Bazinală de Apă) Olt and
dated 22 May 2023.
77 Water management permit for the sub- Water management permit (aviz de
project “Correction of torrents for the river gospodarire a apelor) for the sub-project,
basin Maghernița”. issued by the Water Basin Administration
(Administrația Bazinală de Apă) Siret and
dated 24 March 2024.
78 Water management permit for the sub- Water management permit (aviz de
project “Correction of torrents Fetig, stage gospodarire a apelor) for the sub-project,
III”. issued by the Water Basin Administration
(Administrația Bazinală de Apă) Siret and
dated 24 March 2024.
79 Environmental Protection Agency decision Environmental Protection Agency decision
for the sub-project “Correction of torrents (decizia etapei de încadrare) for the sub-
for the river basin Măieruș, Bacău County”. project, issued by the National
Environmental Protection Agency (Agenţia
Naţională pentru Protecția Mediului) Bacău
and dated 18 May 2020.
80 Environmental Protection Agency decision Environmental Protection Agency decision
for the sub-project “Correction of torrents (decizia etapei de încadrare) for the sub-
for the river basin Grozea, stage III, Bacău project, issued by the National
County”. Environmental Protection Agency (Agenţia
Naţională pentru Protecția Mediului) Bacău
and dated 18 May 2020.
81 Environmental Protection Agency decision Environmental Protection Agency decision
for the sub-project “Correction of torrents (decizia etapei de încadrare) for the sub-
for the river basin Izvorul Negru, stage II, project, issued by the National
Bacău County”. Environmental Protection Agency (Agenţia
Naţională pentru Protecția Mediului) Bacău
and dated 6 September 2022.
82 Environmental Protection Agency decision Environmental Protection Agency decision
for the sub-project “Correction of torrents (decizia etapei de încadrare) for the sub-
for the river basin Pârâul Negru, Bacău project, issued by the National
County”. Environmental Protection Agency (Agenţia
Naţională pentru Protecția Mediului) Bacău
and dated 16 September 2022.
83 Environmental Protection Agency decision Environmental Protection Agency decision
for the sub-project “Correction of torrents (decizia etapei de încadrare) for the sub-
for the river basin and stabilization of the project, issued by the National
21
Valorile și formulările aparțin documentului citat. Data preluării nu reprezintă perioada datelor sau data publicării de către instituție.
Identificarea exactă a documentului colectat
Amprenta SHA-256 permite identificarea versiunii preluate.
6d92c2a23abea1ff81530993192d55903e8d84809fbd0b497db72a28a8fa2b84