Preliminary assessment of the fourth payment request of Romania

Instituția sau publicația sursă
PNRR România, plan și decizii
Data preluării
26.09.2026 17:54
Dimensiunea materialului
2.677,1 KB

Conținutul documentului colectat

Secțiuni și tabele

     “Correction of torrents for the river basin for the project, issued by NCDS ”Marin
     Valea Rea stage II”.                        Drăcea” to the beneficiary Romsilva and
                                                 dated 10 November 2022.
33   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents for the river basin for the project, issued by NCDS ”Marin
     Bucșoița”.                                  Drăcea” to the beneficiary Romsilva and
                                                 dated 3 February 2023.
34   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents for the river basin for the project, issued by NCDS ”Marin
     Pârâul Leșului”.                            Drăcea” to the beneficiary Romsilva and
                                                 dated 3 February 2023.
35   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents Scânteia”.          for the project, issued by Alfrid srl and to
                                                 beneficiary Romsilva and dated 31 August
                                                 2022.
36   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents Valea Lungă”.       for the project, issued by Alfrid srl to the
                                                 beneficiary Romsilva and dated 13
                                                 September 2022.
37   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents Izvorul Govorei”.   for the project, issued by Alfrid srl to the
                                                 beneficiary Romsilva and dated 18 January
                                                 2019.
38   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents Bistricioara, stage for the project, issued by Alfrid srl to the
     II”.                                        beneficiary Romsilva and dated 16 June
                                                 2022.
39   Feasibility study for the sub-project Feasibility study including the project design
     “Correction of torrents for the river basin for the project, issued by Sursa Com srl to
     Maghernița”.                                the beneficiary Romsilva and dated February
                                                 2023.
                                                     Romania provided this document together
                                                     with Evidence No. 59, the DNSH analysis for
                                                     the sub-project.
40   Feasibility study for the sub-project           Feasibility study including the project design
     “Correction of torrents Fetig, stage III”.      for the project, issued by NCDS ”Marin
                                                     Drăcea” to the beneficiary Romsilva and
                                                     dated 3 February 2023.
41   Do No Significant Harm analysis for the sub-    Do No Significant Harm analysis for the sub-
     project “Correction of torrents for the river   project including analysis of its potential
     basin Măieruș, Bacău County”.                   impact on water bodies, issued by Tim Wald
                                                     Consult to the beneficiary Romsilva and
                                                     dated 3 August 2022.
42   Do No Significant Harm analysis for the sub-    Do No Significant Harm analysis for the sub-
     project “Correction of torrents for the river   project including analysis of its potential
     basin Grozea, stage III, Bacău County”.         impact on water bodies, issued by Tim Wald
                                                     Consult to the beneficiary Romsilva and
                                                     dated 4 April 2022.
43   Do No Significant Harm analysis for the sub-    Do No Significant Harm analysis for the sub-
     project “Correction of torrents for the river   project including analysis of its potential
     basin Izvorul Negru, stage II, Bacău            impact on water bodies, issued by Tim Wald

17

Valorile și formulările aparțin documentului citat. Data preluării nu reprezintă perioada datelor sau data publicării de către instituție.

Identificarea exactă a documentului colectat

Amprenta SHA-256 permite identificarea versiunii preluate.

6d92c2a23abea1ff81530993192d55903e8d84809fbd0b497db72a28a8fa2b84