Number and name of the Milestone: RO-C[C2]-I[5]-M[41] Approval of project design
Related Measure: RO-C[C2]-I[5] Integrated flood risk mitigation systems in forest river basins
Qualitative Indicator: Approval of project design
Time: Q1 2023
1. Context:
The objective of this investment is to reduce flood risk to protect people, infrastructure and socio- economic objectives in risk areas, as well as to protect the environment and biodiversity through environmental measures, in particular those relating to ensuring fish migration and ensuring ecological flow. The investment consists of modernisation works for flood protection.
Milestone 41 concerns the approval of the project design for the modernisation works for flood protection.
Milestone 41 is the first step of the implementation of the investment, and it will be followed by milestone 42, related to the construction of the modernisation works for flood protection.
2. Evidence provided:
Name of the evidence Short description
1 Cover note Summary document duly justifying how the
target (including all the constitutive
elements) was satisfactorily fulfilled.
2 Copy of financing contract COD C2/I5 of 1 Signed contract between the Ministry of the
September 2022. Environment, Water Resources and Forestry
and the Romanian National Forest Authority
Romsilva for the task to carry out the
torrential correction project.
3 Endorsement report (aviz) () approving the Endorsement report approving the design
design for the sub-project “Correction of for the sub-project, issued by the Technical
torrents for the river basin Măieruș, Bacău and Economic Committee for Opinion of
County”. Romsilva and dated 26 October 2020.
4 Endorsement report (aviz) approving the Endorsement report approving the design
design for the sub-project “Correction of for the sub-project, issued by the Technical
torrents for the river basin Grozea, stage III, and Economic Committee for Opinion of
Bacău County”. Romsilva and dated 26 October 2020.
5 Endorsement report (aviz) approving the Endorsement report approving the design
design for the sub-project “Correction of for the sub-project, issued by the Technical
torrents for the river basin Izvorul Negru, and Economic Committee for Opinion of
stage II, Bacău County”. Romsilva and dated 24 November 2022.
6 Endorsement report (aviz) approving the Endorsement report approving the design
design for the sub-project “Correction of for the sub-project, issued by the Technical
torrents for the river basin Pârâul Negru, and Economic Committee for Opinion of
Bacău County”. Romsilva and dated 24 November 2022.
7 Endorsement report (aviz) approving the Endorsement report approving the design
design for the sub-project “Correction of for the sub-project, issued by the Technical
torrents for the river basin and stabilization and Economic Committee for Opinion of
of the slope Strâmtura Scaune, pârâul Romsilva and dated 24 November 2022.
14
Valorile și formulările aparțin documentului citat. Data preluării nu reprezintă perioada datelor sau data publicării de către instituție.
Identificarea exactă a documentului colectat
Amprenta SHA-256 permite identificarea versiunii preluate.
6d92c2a23abea1ff81530993192d55903e8d84809fbd0b497db72a28a8fa2b84