Operational Arrangements between the European Commission and Romania
- Instituția sau publicația sursă
- PNRR România, plan și decizii
- Data preluării
- 26.09.2026 17:54
- Dimensiunea materialului
- 5.789,4 KB
Conținutul documentului colectat
Secțiuni și tabele
Qualitative Quantitative indicators Indicative timeline
Related Measure Further
Milestone/ indicators (for targets) for completion Responsibility
Num (Reform or Name specification
Target (for for reporting and Verification mechanism
Investment) (where
milestones) implementation
Unit of necessary)
Baseline Goal Quarter Year
measure
railways of the total (MTI)/Romania
infrastructure railways n Railway This document shall include as an annex
infrastructure Company the following documentary evidence:
investments. (CFR) a) a list of the total projects including a
brief description and a list of all the
projects completed including a brief
description;
b) report by an independent entity
endorsed by the responsible ministry
certifying the percentage of works
completed.
75 Investment 1. Target Kilometres of Kilometre 0 2 851 Q2 2026 Ministry of Summary document duly justifying how
Modernisation new/upgraded s (km) Transport and the target (including all the constitutive
and renewal of operational Infrastructure elements) was satisfactorily fulfilled.
railways railway (MTI)/Romania
infrastructure infrastructure n Railway This document shall include as an annex
Company a list of all the sites/projects where works
(CFR) have been carried out and certified as
completed/accepted by contractor and
contracting authority.
On the basis of a sample that may be selected by the Commission, at a minimum the following documentary evidence shall be submitted for each sites/project selected:
a) Copy of the completion/acceptance certificate, signed by contractor and contracting authority, in accordance with the national legislation. b) copy of all EIA and permits obtained c) certificate issued by MTI , indicating the length of the railway, that the railways are conforming to
22
Valorile și formulările aparțin documentului citat. Data preluării nu reprezintă perioada datelor sau data publicării de către instituție.
Identificarea exactă a documentului colectat
Amprenta SHA-256 permite identificarea versiunii preluate.
c72f4c753645594284a4468173145d1a9c1d7855c09b5e5aab89bf33949e6313