ANNEX to the COUNCIL IMPLEMENTING DECISION amending Implementing Decision of 29 October 2021 on the approval of the assessment of the recovery and resilience plan for Romania
- Instituția sau publicația sursă
- PNRR România, plan și decizii
- Data preluării
- 26.09.2026 17:54
- Dimensiunea materialului
- 3.786,9 KB
Conținutul disponibil în colecție
Textul documentului
icative
Quantitative indicators
timeline for
(for targets)
Related Measure Qualitative completion
Seq. Milestone Description of each milestone
(Reform or Name indicators
Num. / Target and target
Investment) (for milestones) Unit of
Baseline Goal Quarter Year
measure
30 Reform 2. Reform Milestone Entry into force Provision in the Q2 2022 Entry into force of the
of the of the law indicating legislative act setting up the
management legislative act the entry into inter-institutional committee to
system for setting up the force of the analyse the legal framework
protected natural inter- legislative act applicable to sectors with an
areas for the institutional impact on biodiversity, namely
European committee to education, agriculture, forestry,
Biodiversity analyse the hunting, tourism, spatial
Strategy legal organisation, transport and
framework energy.
applicable to The Committee shall be steered
sectors with an by the Ministry of the
impact on Environment, Waters and
biodiversity Forests and it shall include the
line ministries and the
subordinated authorities
responsible for the relevant
sectors: education, agriculture,
forestry, hunting, tourism,
spatial organisation, transport
and energy.
The committee shall prepare
proposals to revise the legal
framework in the light of up-to-
date information on the
distribution and dynamics of
14452/25 ADD 1 25
ECOFIN 1A EN
Indicative
Quantitative indicators
timeline for
(for targets)
Related Measure Qualitative completion
Seq. Milestone Description of each milestone
(Reform or Name indicators
Num. / Target and target
Investment) (for milestones) Unit of
Baseline Goal Quarter Year
measure
the conservation status of
species and habitats.
31 Reform 2. Reform Milestone Entry into force Provision in the Q1 2026 Entry into force of the
of the of the law indicating legislative act approving the
management legislative act the entry into National Biodiversity strategy
system for applicable to force of the that shall also apply to the
protected natural sectors with an legislative act education, agriculture, forestry,
areas for the impact on hunting, tourism, spatial
European biodiversity organisation, transport and
Biodiversity energy sectors.
Strategy
14452/25 ADD 1 26
ECOFIN 1A EN
C. COMPONENT 3: WASTE MANAGEMENT
The objective of the component is to accelerate the expansion and modernisation of waste
management systems in Romania with a focus on separate collection, prevention, reduction, re-use
and recovery to comply with the transition to the circular economy.
The component is comprised of one reform and four investments, out of which one subinvestment
of the investment 1 and one investment are financed through non-repayable financial support.
The measures included in the component are expected to address some of the challenges highlighted
by the country-specific recommendation to focus investment on the green and digital transition, in
particular on environmental infrastructure among others (country-specific recommendations 2019
and 2020).
It is expected that no measure in this component does significant harm to environmental objectives
within the meaning of Article 17 of Regulation (EU) 2020/852, taking into account the description
of the measures and the mitigating steps set out in the recovery and resilience plan in accordance
with the DNSH Technical Guidance (2021/C58/01).
C.1. Description of the investments through non repayable financial support
Investment 1.a. Construction of voluntary waste collection centres at county level or at
city/municipality level
The objective of this sub-investment is to construct voluntary waste collection centres. The
investment consist in construction of voluntary collection centres serving communities of up to 50
000 inhabitants.
This sub-investment is complemented by the other sub-investments of Investment 1 (1.b, 1.c and
1.d).
Investment 3. Public monitoring, control and institutional capacities for waste management
The objective of this investment is to increase public monitoring, control and institutional capacities
for waste management.
The investment consist in equiping with digital equipment the respective public authorities for
waste management monitoring, control and reporting activities.
14452/25 ADD 1 27
ECOFIN 1A EN
C.2. Milestones, targets, indicators, and timetable for monitoring and implementation for non repayable financial support
Indicative
Quantitative indicators (for
Related Qualitative timeline
targets)
Seq. Measure Milestone/ indicators for completion Description of each milestone and
Name
Num. (Reform or Target (for Unit target
Investment) milestones) of Baseline Goal Quarter Year
measure
49 Investment 1.a Target Voluntary 0 300 Q2 2026 Work completion reception certificate of
Construction of collection construction of 300 voluntary collection
voluntary centres centres serving communities of up to 50
collection constructed 000 inhabitants will be provided.
centres The centres ensure the separate
collection of household waste.
56 Investment 3.a Milestone Purchase of Reception Q3 2025 Reception certificate of equipment
Public digital certificates purchased for 43 Commissioners of the
monitoring, equipment Environmental Guard for waste
control and management monitoring and control
institutional activities. The following equipment may
capacities for include among others:
waste - 1 ICT integrated system servicing the
management 43 Commissioners;
- 8 truck scanning systems;
- 271 dash cam video cameras;
- 16 unmanned Aerial Vehicles;
- 8 utility vehicles equipped with radio
communication for the transport of
monitoring equipment;
- 709 body worn Cameras.
In order to ensure that the measure
complies with the ‘Do no significant
harm’ Technical Guidance
(2021/C58/01), the vehicles purchased
under this measure shall be the best-
14452/25 ADD 1 28
ECOFIN 1A EN
available-technology from an
environmental point of view.
57 Investment 3.b Target Delivery of 400 Number 0 400 Q4 2025 Control documents of 400 control
Public control missions conducted by the National
monitoring, missions using Environmental Guard Commissioners
control and digital using digital equipment.
institutional equipment
capacities for
waste
management
14452/25 ADD 1 29
ECOFIN 1A EN
C.3. Description of the reforms and investments for the loan
Reform 1. Support to waste management governance to a
← Înapoi la începutul extrasului
Extrasul poate avea altă structură decât documentul original. Data preluării nu reprezintă perioada statistică sau data publicării de către instituție.
Identificarea exactă a documentului colectat
Amprenta SHA-256 permite identificarea versiunii preluate.
2d42cc042ec0b415a2656a4949f50e85266b99d38d037ae1e7b0516b19e5384b